How to specify to consider capacity values of sub resources in calculating production times
Steps:
1.Click on the [Scheduling Parameter Settings] button on the toolbar. Or, select [Schedule] – [Scheduling Parameter Settings…] from the main menu. Properties of the current scheduling parameter will be displayed in the properties window.
2.Select the General tab from the properties window.
3.Click the Value cell of the property “Production time calculation” and select “Longest time sub resource” from the dropdown list box.