How to specify the minimum and maximum quantities a resource can produce at once
Steps:
1.In the resource table, specify the maximum quantity that the resource can produce at once in the “Resource split size MAX” field of the target resource.
2.In the resource table, specify the minimum quantity that the resource can produce at once in the “Resource split size MIN” field of the target resource.
If you specify zero for both the resource split size MIN and MAX, there will be no constraint.
If the production quantity of an operation is smaller than the resource split size MIN, the operation’s production quantity will be increased to the resource split size MIN. (However, the increased quantity cannot be reflected onto the input item.)
If the production quantity of an operation is greater than the resource split size MAX, the operation will be automatically split.