How to round the start time and end time of operations

Steps:

1.In the resource table, enter the start/end time rounding unit in the “Start/end time round unit” field of the target resource.
2.The time to be rounded will be determined depending on the assignment direction in which an operation is assigned.
Assignment direction Time to be rounded
Forward Production start time
Backward Production end time

If you want to round the production start time and production end time in the same unit, specify the same unit as the production time round unit.