How to specify for an item that split operations will be performed in parallel
Steps:
1.Select [Table View] – [Item] from the menu bar. The item table will be displayed.
2.In the item table, specify a value in the “Split parallel number” field of the target item.
3.Display the resource Gantt chart and click on the [Reschedule] button. Split operations will be assigned in parallel to resources as many as the number you specified in the “Split parallel number” field.