How to specify that the resource quantity of a resource will be constrained

Steps:

1.In the resource table, set the property “Resource quantity constraints” of the target resource to “Constrained”.
2.When the property “Resource quantity constraints” of a resource is set to “Constrained”, operations will be assigned to that resource in a way that the resource quantity will not exceed the value specified in the calendar table.