Ver.13.0.1 Group assign option for realizing constraints during simultaneous processing
As shown on the left and right of the body, manufacturing orders are registered and scheduled as separate orders, but there are cases when a given process gets simultaneously assigned owing to processing accuracy or tinting issues.
The group assignment option meets such needs.
It allows grouping of multiple specified operations and assigning them so that their production start times are the same.
Further, when an operation is moved, this is reflected in real time, thereby allowing scheduling that takes into account even constraints that are set simultaneously, whether during rescheduling or manual revision.
This is further explained in a video.
[Click here to download]
Asprova HELP
-> http://lib.asprova.com/onlinehelp/en/AS2003HELP00777650.html
-> [Optional Features]-[Group assign option] – HelpNo.:777650
-> http://lib.asprova.com/onlinehelp/en/AS2003HELP00925000.html
-> [Samples]-[T: Group assign] – HelpNo.:925000